Project Managing Asia's Data Centre Boom: Steps to Success


APAC is catching up fast in a market that has traditionally been dominated by North America. By 2020, if predictions are correct, the region will be the biggest data centre market in the world. Adding to Asia’s concentration of data centre capacity in Japan, Hong Kong and Singapore, come scores of projects in Indonesia, India, Korea, Taiwan and China.
The sheer number of projects, combined with the variety of cultural and regulatory environments, presents a raft of challenges in this fast-moving era. From a project management perspective, the secret of success is to do the basic things well: good planning, the right people and execution against the plan.
1. Proper planning
Time is what we don’t have. But our analysis shows it’s a false economy to cut back on time for planning. Poor planning is the most common cause of cost and time overruns on data centre projects in the region.
Macro-level planning at the feasibility stage is vital. Employ an expert early to ask questions about location, size, IT load, operational specifications and power, all considered with business data and forecasting in hand. The impact of local planning permissions and other approvals should be included in the assessment.
Failing to set realistic cost and time constraints can lead to poor decisions down the line. For example, if the timeline is too tight, design-and-build procurement may look like the only option, despite the fact that the local market is not set up to deliver through this route.
2. Procurement strategy
From a turnkey project to one where each element is individually procured, we see many options for delivering data centres in APAC.
Selecting the right one depends on multiple factors including the way the local market operates, immediacy of need and appetite for risk.
In our experience, employing the right designer—either directly or as part of a design-build team - can be the difference between success and failure. A track record in data centres isn’t enough. Assess the experiences and capabilities of the individuals who will be working on the project day-to-day.
As a rule of thumb, design-build contracts tend to work well in more mature markets, whereas a more traditional design-bid-build route can be safer in newer markets.
Fewer packages means fewer interface risks, but owners will almost always want to split out some business-critical elements such as air conditioning or key mechanical or electrical components to ensure they are right. It’s a case of balancing the risks and costs to find the sweet spot.
3. Cultural awareness
As a rule of thumb, design-build contracts tend to work well in more mature markets, whereas a more traditional design-bid-build route can be safer in newer markets
In newer markets, the supply chain may not be aware of industry jargon. Documents and communications should use plain language with key terms well defined for the whole team.
Practices and standards relating to safety and quality will vary hugely. Risks are higher in markets with relatively unskilled labour. Failing to manage these issues can result in reputational damage to a company and its brand.